SIPs Panels Ltd were appointed to fulfil the superstructure for a new two-storey school building at Lawford Primary School in Essex.
SPL designed, manufactured and installed a hybrid two-storey SIPs structure with main contractor Barnes Construction.
To deliver this structure, we used high performance load bearing SIPs for the external wall, with primary structural element, internal timber frame walls and engineered timber joist roof cassettes.
We also incorporated PCC hollow-core separating floor and PCC stairs as part of the SPL SIPs structure package.
SPL fulfilled works and handed over the superstructure to Barnes Construction after 8 weeks in May 2021.